Skanska.com
Follow Us
Beaverton High School Modernization
Beaverton School District
Project Updates
Home
Project Updates
Upcoming Impacts
Live Camera
August 2027
Beaverton High School Final Completion Rendereings
(Scroll to the right and left to see more pictures)
Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
January 2024
Project Updates
Home
Project Updates
Upcoming Impacts
Live Camera
Skanska.com
Follow Us
Beaverton High School Modernization
Beaverton School District
Tap on the icons to learn more.
January 2024
BHS New Building
Demolition & Abatement of Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
January 2024
Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
Continued Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
February 2024
BHS New Building
Demolition & Abatement of Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
February 2024
February 2024
Continued Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
BHS New Building
Demolition & Abatement of Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
February 2024
Completion of Demolition & Abatement for Merle Davies Building
(Scroll to the right and left to see more pictures)
March 2024
BHS New Building
Completion of Demolition & Abatement for Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
March 2024
March 2024
Completion of Demolition & Abatement for Merle Davies Building
(Scroll to the right and left to see more pictures)
BHS New Building
Completion of Demolition & Abatement for Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
March 2024
BHS New Building
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
April 2024
BHS New Building
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
April 2024
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
April 2024
April 2024
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
May 2024
BHS New Building
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
May 2024
May 2024
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
BHS New Building
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
May 2024
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
June 2024
BHS New Building
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
June 2024
June 2024
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
BHS New Building
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
June 2024
Continued Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
July 2024
BHS New Building
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
R-Tank installment & contractor temporary parking layout east of track
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
July 2024
July 2024
Continued Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
R-Tank installment & contractor temporary parking layout east of track
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
July 2024
Slab On Grade Pour, Tilt Panel Pour, R-Tank Installation, & Continued Civil and MEP Work.
(Scroll to the right and left to see more pictures)
August 2024
BHS New Building
Slab On Grade Pour, Tilt Panel Pour, & Continued Civil and MEP Work.
Sports Field
Check back weekly for updates!
Track & Field Renovation
R-Tank installment & contractor temporary parking layout east of track
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
August 2024
August 2024
Slab On Grade Pour, Tilt Panel Pour, R-Tank Installation, & Continued Civil and MEP Work.
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Grade Pour, Tilt Panel Pour, & Continued Civil and MEP Work.
Sports Field
Check back weekly for updates!
Track & Field Renovation
R-Tank installment & contractor temporary parking layout east of track
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
August 2024
Crane Assembly, Structural Steel Erection, SOG Pours & Continued Civil And MEP Installation
(Scroll to the right and left to see more pictures)
September 2024
BHS New Building
Crane Assembly, Structural Steel Erection, SOG Pours & Continued Civil And MEP Installation
Sports Field
Check back weekly for updates!
Track & Field Renovation
R-Tank installment & contractor temporary parking layout east of track
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
September 2024
September 2024
Crane Assembly, Structural Steel Erection, SOG Pours & Continued Civil And MEP Installation
(Scroll to the right and left to see more pictures)
BHS New Building
Crane Assembly, Structural Steel Erection, SOG Pours & Continued Civil And MEP Installation
Sports Field
Check back weekly for updates!
Track & Field Renovation
R-Tank installment & contractor temporary parking layout east of track
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
September 2024
Tilt Panel Erection, Slab On Metal Deck Installation, Structural Steel Erection, & Continued Civil And MEP Installation.
(Scroll to the right and left to see more pictures)
October 2024
BHS New Building
Tilt Panel Erection, Slab On Metal Deck Installation, Structural Steel Erection & Continued Civil And MEP Installation
Sports Field
Check back weekly for updates!
Track & Field Renovation
Contractor temporary parking completed.
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
October 2024
October 2024
Tilt Panel Erection, Slab On Metal Deck Installation, Structural Steel Erection, & Continued Civil And MEP Installation.
(Scroll to the right and left to see more pictures)
BHS New Building
Tilt Panel Erection, Slab On Metal Deck Installation, Structural Steel Erection & Continued Civil And MEP Installation
Sports Field
Check back weekly for updates!
Track & Field Renovation
Contractor temporary parking completed.
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
October 2024
Slab On Metal Deck Installation, Fireproofing, Structural Steel Erection, Civil Excavation & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
November 2024
BHS New Building
Slab On Metal Deck Installation, Structural Steel Erection, Fireproofing, Civil Excavation & MEP Installation
Sports Field
Check back weekly for updates!
Track & Field Renovation
Contractor temporary parking completed.
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
November 2024
November 2024
Slab On Metal Deck Installation, Fireproofing, Structural Steel Erection, Civil Excavation & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Metal Deck Installation, Structural Steel Erection, Fireproofing, Civil Excavation & MEP Installation
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
November 2024
Slab On Metal Deck & Grade, Fireproofing, Structural Steel Erection, Civil Excavation, Exterior/Interior Framing & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
December 2024
BHS New Building
Slab On Metal Deck & Grade, Fireproofing, Structural Steel Erection, Civil Excavation, Exterior/Interior Framing & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
December 2024
December 2024
Slab On Metal Deck & Grade, Fireproofing, Structural Steel Erection, Civil Excavation, Exterior/Interior Framing & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Metal Deck & Grade, Fireproofing, Structural Steel Erection, Civil Excavation, Exterior/Interior Framing & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
December 2024
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
January 2025
BHS New Building
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
January 2025
January 2025
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
January 2025
Slab On Metal Deck, Fireproofing, Structural Steel Top Out, Civil Sitework, Interior/Exterior Door Install, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
February 2025
BHS New Building
Slab On Metal Deck, Fireproofing, Structural Steel Top Out, Civil Sitework, Interior/Exterior Door Install, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Temporary Javelin Field Install.
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
February 2025
February 2025
Slab On Metal Deck, Fireproofing, Structural Steel Top Out, Civil Sitework, Interior/Exterior Door Install, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Metal Deck, Fireproofing, Structural Steel Top Out, Civil Sitework, Interior/Exterior Door Install, Exterior Facade & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Temporary Javelin Field Install.
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
February 2025
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Interior/Exterior Door Install, Exterior Facade, Metal Wall Panel Install, Brick Installation, & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
March 2025
BHS New Building
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Interior/Exterior Door Install, Exterior Facade, Metal Wall Panel Install, Brick Installation, & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Temporary Javelin Field Install.
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
March 2025
March 2025
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Interior/Exterior Door Install, Exterior Facade, Metal Wall Panel Install, Brick Installation, & Mechanical/Electrical/Plumbing (MEP) Installation.
(Scroll to the right and left to see more pictures)
BHS New Building
Slab On Metal Deck, Fireproofing, Structural Steel, Civil Sitework, Interior/Exterior Door Install, Exterior Facade, Metal Wall Panel Install, Brick Installation, & Mechanical/Electrical/Plumbing (MEP) Installation.
Sports Field
Check back weekly for updates!
Track & Field Renovation
Temporary Javelin Field Install.
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
March 2025