Beaverton High School Modernization
Beaverton School District
The new Beaverton High School will be a 300,500 square foot, three-story building surrounding an enclosed courtyard. Work includes new parking lots, athletic fields and landscaping.
Project Information
New gymnasium and sports fields
New parking lots and landscaping
Demolition of the existing school
Home
Project Updates
Upcoming Impacts
Live Camera
Meet the team
Trevor Wyckoff
Account Manager
Alan Halleck
Sr. Project Manager
Patrick Bestebreur
Project Manager
Patrick Sullivan
Project Manager
Tyler Miller
Project Engineer
David Quivey
Lead Superintendent
Austin McCabe
Area Superintendent
Sam Stinson
Project Engineer
Tyler Martens
Project Manager
Home
Project Updates
Upcoming Impacts
Live Camera
Patrick Sullivan
Project Manager
Patrick Bestebreur
Project Manager
Alan Halleck
Sr. Project Manager
Trevor Wyckoff
Account Manager
Milestone Schedule
Merle Davies Demolition
Foundations
BHS Construction
Milestone 4
Milestone 5
Milestone 6
Milestone 7
Milestone 8
Milestone 9
Substantial completion
Tyler Miller
Project Engineer
David Quivey
Lead Superintendent
John Medvec
Sr. Design Integration Manager
2027
2026
2025
2024
Existing high school demolition & abatement completed in January of 2027.
Construction continued. Check back for updates!
Construction continued. Check back for updates!
Merle Davies Building demolition & abatement begins in January of 2024.
Beaverton High School rebuild begins in March of 2024.
Hover over each year & date to learn about the schedule
Timeline
July 2027
Parking lot and sports field completed & open July of 2027.
Beaverton High School completed & open in July of 2026.
Commencement of demolition & abatement for exisiting high school in July of 2026.
Parking lot and sports field construction to begin in July of 2026.
July 2026
Fabricio Costa
Sr. Project Engineer
Kevin Rowe
Asst. Superintendent
Troy Boardman
Superintendent
Fabricio Costa
Sr. Project Engineer
Sam Stinson
Project Engineer
Tyler Martens
Project Manager
Click here to find out more about the Beaverton School District/Beaverton High School
Rick Burnett
EHS Manager
Susan Amash
Project Administrator
Doug Hobb
Concrete Foreman
Jason Brewer
Concrete Foreman
Krys Lukesh
Superintendent
Troy Boardman
Superintendent
Rick Burnett
EHS Manager
Kevin Rowe
Asst. Superintendent
Susan Amash
Project Administrator
John Medvec
Sr. Design Integration Manager
Krys Lukesh
Superintendent
Austin McCabe
Area Superintendent
Doug Hobb
Concrete Foreman
![](https://media-s3-us-east-1.ceros.com/skanska/images/2023/11/01/5ed9f5792b7ef1e0d967cc3f99317096/susan-amash-glasses-master-sm.jpg)
Skanska.com
Follow Us
Beaverton High School Modernization
Beaverton School District
Project Updates
Home
Project Updates
Upcoming Impacts
Live Camera
August 2027
Beaverton High School Final Completion Rendereings
(Scroll to the right and left to see more pictures)
Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
January 2024
Project Updates
Home
Project Updates
Upcoming Impacts
Live Camera
Skanska.com
Follow Us
Beaverton High School Modernization
Beaverton School District
Tap on the icons to learn more.
January 2024
BHS New Building
Demolition & Abatement of Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
January 2024
Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
Continued Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
February 2024
BHS New Building
Demolition & Abatement of Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
February 2024
February 2024
Continued Demolition & Abatement of Merle Davies Building
(Scroll to the right and left to see more pictures)
BHS New Building
Demolition & Abatement of Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
February 2024
Completion of Demolition & Abatement for Merle Davies Building
(Scroll to the right and left to see more pictures)
March 2024
BHS New Building
Completion of Demolition & Abatement for Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
March 2024
March 2024
Completion of Demolition & Abatement for Merle Davies Building
(Scroll to the right and left to see more pictures)
BHS New Building
Completion of Demolition & Abatement for Merle Davies Building
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
March 2024
BHS New Building
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
April 2024
BHS New Building
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
April 2024
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
April 2024
April 2024
Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
May 2024
BHS New Building
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
May 2024
May 2024
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
BHS New Building
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
May 2024
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
June 2024
BHS New Building
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Cick on the icons to learn more.
June 2024
June 2024
Slab On Grade Pour, Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing for BHS Rebuild
(Scroll to the right and left to see more pictures)
BHS New Building
Continued Earthwork, Underground Utilities, Building Footings/Rebar, & Foundation Waterproofing
Sports Field
Check back weekly for updates!
Track & Field Renovation
Check back weekly for updates!
Parking Lot Addition
Check back weekly for updates!
Tap on the icons to learn more.
June 2024
Skanska.com
Follow Us
Beaverton High School Modernization
Beaverton School District
Upcoming Activities
Parking Closure
Location:
Impacts:
Notes:
Date:
Time:
Demolition
Traffic Control
Location:
Impacts:
Notes:
Date:
Time:
Location: Merle Davies Building
Activities: Demolition & Abatement
Date: January 2024 - March 2024
Home
Project Updates
Upcoming Impacts
Live Camera
Skanska.com
Follow Us
Upcoming Activities
Home
Project Updates
Upcoming Impacts
Live Camera
Beaverton High School Modernization
Beaverton School District
Location: Merle Davies Building
Activities: Demolition & Abatement
Date: January 2024 - March 2024
Location:
Impacts:
Notes:
Date:
Time:
BHS Rebuild Site
Location: BHS Rebuild Site
Activities:
- Slab On Grade Concrete Pours
- Earthwork
- Underground Utilities
- Concrete Building Footings & Rebar
- Foundation Waterproofing
See Below For Site Access (07/08 - 08/02)
Date: April 2024 - July 2024
BHS Rebuild Site
Location: BHS Rebuild Site
Activities:
- Slab On Grade Concrete Pours
- Earthwork
- Underground Utilities
- Concrete Building Footings & Rebar
- Foundation Waterproofing
See Below For Site Access (07/08 - 08/02)
Date: April 2024 - July 2024