Outline of other contracting party’s claims
Notice of intervention
Other contracting party’s answer
Designation of the third-person decider
Outline of applicant’s claims
Third-person decider’s decision
Payment (if applicable)
Dispute settlement scheme
* The third-person decider may extend the deadline by 15 days or longer if the parties agree. The dispute resolution scheme lasts a total of 80 days, or 95 days if the third-person decider extends the deadline by 15 days to reach a decision.
5 days
15 days
20 days
*extension
50 days
Response to the request to consolidate disputes
Third-person decider’s decision on consolidating disputes
request for intervention
claimant's detailed statementof claim