Zero Punchlist
Three-Phase
Quality Control
Preparatory
Initial
Follow Up
Pre-construction meeting by definable feature of work
Initial inspection with established checklists at the start of definable features of work
Continuous inspections with established checklists by areas
Perform punchlist by smaller areas for each trade throughout the project to achieve Zero Punchlist at the end of the project.
To achieve Zero Punchlist we implement the "Punch as you Build" philosophy.
Use established pre-construction meeting agendas for consistency
Use established checklists in BIM360 for lessons learned and consistency
Use BIM360 to closeout areas throughout the project with issues management visible to the owner
Punch as you Build
Project Kickoff
Pre-con Meeting
Performing Work
Establish checklists to be used from Kickoff meeting agenda
Establish project locations in BIM360 with VDC team
On-board subcontractors to BIM360
Review checklist and locations with Subcontractor and establish expectations
Contact VDC/QC to visit site and train subcontractors
Track checklists by location with subcontractors and create ongoing punchlist