Intelligent Planning. Optimized Well Cycle Time.

Closing the gap between Operators and Drilling Contractors.

SmartPLAN®  is the rig plan execution engine for the drillers and crew. It enhances operational efficiency by providing clear objectives and understandable execution protocols and procedures within an activity sequence roadmap to perform tasks more effectively.

READ MORE

Enhance

Efficiency

Increase Productivity

Improve 

Accuracy

Scale Best Practices

SmartPLAN Benefits 

Optimized Operations

Enhanced Procedural Adherence

Efficient Onboarding & Training

View SmartPLAN Features

SmartPLAN Features 

Time and Activity Metrics

Pre-Tour Planning

Real-time notifications

View SmartPLAN Benefits

SmartPLAN End-to-End Journey

Well Program

Consumes the well program designed by Engineers or Software

Create the 

SmartPLAN®

Through the SmartPLAN® Builder application we create all customer-approved activity sequences for the rig

Execution

Activate, start, and execute the plans while automatically filling out toursheet.

Tracking

Monitor performance and real time tracking of the well

SmartPLAN Impact

Improved well cycle time

Improved procedural adherence

Reduced flat times

SmartPLAN Case Studies 

-25%

10

9

8

7

6

5

4

3

2

1

0

22,000

20,000

18,000

16,000

14,000

12,000

10,000

8,000

6,000

4,000

2,000

0

20K

21K

18K

9.10

9.50

9.00

8.20

7.50

7.10

Average flat time reduction per well:

2.4 days

PAD 1

PAD 2

PAD 3

WTX Permian Pad to Pad

View results from 5 rigs across 4 quarters

Flat

Drill

Depth

ND Bakken Pad to Pad

WTX Delaware Pad to Pad

Smart PLAN Case Study | Avg Flat & Drill Time (Days) / App Utilization Compliance %

21.50 DAYS

17.20 DAYS

16.90 DAYS

14.50

99%

99%

97%

91%

13

12

11

10

9

8

7

6

5

4

3

2

1

0

100

95

90

85

80

75

70

65

60

55

50

45

40

12.89

Days

Compliance %

-49%

9.36

8.80

8.61

8.10

7.80

7.90

6.60

Q3'23

Q4'23

Q1'24

Q2'24

Well Cycle Time

Flat

Drill

SP Compliance

These results cover 5 rigs across the Permian Basin with an average depth well drilled to 19,000 ft and a total of 102 three-string wells drilled.

Close Bubbles

Deployment Strategy 

1

Initial Customer Session

2

Rig Install

3

SmartPLAN® Builder

4

Crew Training

5

Crew Utilization

6

Performance Feedback