Skanska USA is one of the largest construction and development companies in the U.S., serving a broad range of clients. Headquartered in New York City with offices in 29 metro areas, we have more than 7,600 employees committed to being leaders in safety, project execution, sustainability, ethics and people development.
We have been active in the Pacific Northwest market since 1946. For the last five years, our local team has won an average of $625 million of work each year across a wide range of markets—including government, commercial, healthcare and high-tech—in both the public and private sectors. With a dedicated staff of more than 300 employees in Oregon and Southwest Washington, Skanska combines local presence with national resources to build a more sustainable future for our customers and communities.
Mountain View High School Project Updates
Project Update: March 1 - 6
Highlights from this week
Lower level of the auditorium
This picture shows the lower level of the auditorium. This week the lower slab was prepped to be poured with concrete.
These are the forms for the tilt panels. These will be cast in concrete and later erected to become the walls in the auditorium and performing arts building.
Tilt panel forms
New locker room tilt panels
Seen here are the tilt panels for the new lockers rooms. In just a week these panels will be standing and the athletic wing will have vertical walls.
Click on the play icon below to learn more.
22250 Crane
This week a 22250 Crane was built on site in preparation for the start of tilt panel erection next week in the athletic wing of the new school.
Science Classroom Building
Activity: Stair core block complete, ongoing misc. steel and decking install
Science Classroom Building
Activity: Structural steel erection – misc. steel and decking install
CTE Classroom Building
Activity: Under slab plumbing and electrical
Classroom Building
Activity: Vapor barrier and rebar install
Performing Arts Building
Activity: Underground Plumbing, fine grading, electrical under slab conduit, slab and tilt panel forming
Commons Area
Activity: Excavate east mat and spread footings
Athletic Wing
Activity: Completed tilt panels and prep for panel erection
Click on the play icon to learn more.
Tap icons for more information
Project Update: March 8 - 12
Steel Columns
This week steel columns are being placed in one of the classroom buildings.
Tilt Panels
Seen here are the tilt panels being placed by a crane. In only a week all of the walls in the new athletic wing were erected.
Athletic Building
This photo shows the new athletic building that will have a new main gym, auxilary gym, flex training room, wresting room and multiple locker rooms.
Classroom Buildings
This picture shows the construction of the classroom building on the South end of the site.
Photos from this week
Project Update: March 15-20
Highlights from this week
Tap icons for more information
Science Classroom Building
Activity: Mechanical, Electrical and Plumbing Layout and inserts are underway
Science Classroom Building
Activity: Mechanical, Electrical and Plumbing Layout and inserts are underway
CTE Classroom Building
Activity: Electrical underground complete, working on radon piping installation.
Classroom Building
Activity: Finish slab on grade work in North building, structural steel erection in South building
Performing Arts Building
Activity: Tilt panel construction
Commons Area
Activity: Excavate east mat and spread footings
Athletic Wing
Activity: Welding connections, grouting tilt panels, removing casting beds
Tap here to see what is happening LIVE
Project Update: March 22-April 3
Clasroom Building
This photo shows the new classroom building and the stair tower installed for access to each level.
Tilt Panels
Seen here are the tilt panels being finished after the concrete was poured earlier in the day.
Level 2 Layout
This photo shows the mechanical, electrical and plumbing (MEP) layout work happening on level 2 of the classroom buildings.
Althletic Building
This picture shows the joists in the new wrestling room.
Highlights from this week
Highlights from this week
Click icons for more information
Science Classroom Building
Activity: Level 2 slab on metal deck (SOMD) poured. Level 3 SOMD forming underway
Science Classroom Building
Activity: Level 2 slab on metal deck poured.
CTE Classroom Building
Activity: Forming completed. Vapor barrier installed. Rebar being installed.
Classroom Building
Activity: Structural steel columns and beams being installed. Decking completed in South building
Performing Arts Building
Activity: Tilt Panels are poured and are being prepped for panel erection.
Commons Area
Activity: Area being used for steel laydown
Athletic Wing
Activity: West side steel and truss install. East side bent plates are being installed. Tilt panel caulking in progress.
Project Update: April 5-17
Athletic Building
This photo shows a crane placing metal decking in the new athletic building
Roof Level Work
Seen here are a few members of the decking crew installing metal decking at the roof level on one of the classroom buildings.
Slab on Metal Deck
This photo shows the concrete being finished on level 2 of the classroom wing.
Site Activity
This picture shows the last tilt panels being poured near the the future auditorium
Progress Photos
Progress Photos
Site Overview
This photo shows the overall site progress as of April 30th, 2021
Skybridge
This photo shows the construction of the skybridge that connects two of the new classroom buildings.
Tilt Panels
This photo shows the largest concrete tilt panel on this project weighing in at 240,000lbs!
Classroom Building
This picture shows exterior framing being installed on the north side of one of the classroom buildings
Progress Photos
Project Update: April 19-30
Drone Photos
Click the arrows to see more drone photos
Site Overview
This photo shows the overall site progress as of May 12th, 2021.
Locker Rooms
This photo shows the work happening in the future locker rooms. These rooms will be poured with concrete by the end of the week.
Theater Catwalk
This photo shows one of the new catwalks in the theater.
Building Mock-Up
This picture shows the nearly completed building Mock-up.
Progress Photos
Project Update: May 3-15
Project Highlights
Click on icons for more information
Science Classroom Building
Activity: Exterior framing is ongoing. Roofing activities have started.
Science Classroom Building
Activity: Exterior framing work is ongoing. Ductwork staging and installation started.
CTE Classroom Building
Activity: Steel erection and bent plate installation is ongoing.
Classroom Building
Activity: Stair tower is currently being constructed. Concrete slab-on-metal deck was poured on level 3
Performing Arts Building
Activity: Roof beams and catwalks are being installed.
Commons Area
Activity: Footing excavation work is ongoing.
Athletic Wing
Activity: Completing underground electrical and plumbing. Prepping for concrete pour in Locker Rooms.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Exterior framing is ongoing. Interior wall framing and Mechanical, Electrical and Plumbing (MEP) rough-in is ongoing.
Science Classroom Building
Activity: Exterior framing work is ongoing. Ductwork staging and installation ongoing.
CTE Classroom Building
Activity: Miscellaneous steel and bracing install and welding is ongoing.
Classroom Building
Activity: CMU stair tower is complete. Level 2 slab-on-metal deck (SOMD) was poured.
Performing Arts Building
Activity: Steel erection and decking is ongoing. Interior under slab conduit is being installed.
Commons Area
Activity: Concrete columns poured, Steel erection is ongoing.
Athletic Wing
Activity: Concrete Masonry Unit (CMU) walls are being constructed in the locker rooms.
Site Overview
Overall site progress as of May 28th, 2021.
Stair Installation
Stairs are being installed in the new classroom building.
Concrete Columns
These are the concrete columns that will support the future library.
Exterior Framing
Exterior framing work is ongoing on the North side of the new classroom wing.
Progress Photos
Project Update: May 17-June 4
June 3rd Beam Signing
On June 3rd, 2021 Students attending Mountian View High School were invited to commemorate the steel construction of their new school by signing one of the beams near the new main entrance.
On June 3rd, 2021 Students attending Mountian View High School were invited to commemorate the steel construction of their new school by signing one of the beams near the new main entrance.
CTE Classroom Building
Progress on the CTE classroom building.
Exterior Framing
Framing continues on the classroom building on the South end of the site.
Theater Catwalks
The catwalks in the theater are installed and the braces holding up the walls will be removed starting next week.
Overall Site Photo
Overall site progress as of 6/10/2021.
Drone Photos
Project Update: June 7-11
Interior Framing
Interior framing and rough in continues in the classroom buildings.
Mechanical Duct Rough-In
Mechanical duct rough-in is ongoing in the classroom buildings.
Commons Building
Structural steel erection continues in the commons building.
Overall Site Photo
Overall site progress as of 6/18/2021.
Progress Photos
Project Update: June 14-18
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Wall framing, sheathing and interior mechanical, electrical and plumbing rough-in is ongoing.
Science Classroom Building
Activity: Weather barrier installation and interior mechanical, electrical and plumbing rough-in is ongoing.
CTE Classroom Building
Activity: Mechanical, electrical and plumbing inserts are being installed on level 2.
Classroom Building
Activity: Exterior framing has started. Polished concrete placement is ongoing.
Performing Arts Building
Activity: Brace removal is ongoing at the stage and theater area. Bent plate install and conduit connection work continues.
Commons Area
Activity: Steel erection is ongoing. Area is being prepped for deck install.
Athletic Wing
Activity: Concrete Masonry Unit (CMU) walls are being constructed in the locker rooms.
Project Update: June 21 - July 9
One Year Later
One year ago, the first drone photos were taken before construction began on Mountain View High School. Click through the photos below to see the progress made in just a year.
August 2020
June 2020
September 2020
October 2020
November 2020
December 2020
January 2021
February 2021
March 2021
April 2021
May 2021
June 2021
One Year of Progress
June 2021
June 2020
Exterior Weather Barrier
Weather barrier is being installed on the new athletic building.
Commons Building
Metal decking is now installed on the commons building.
Classroom Wing
Interior framing, plumbing and mechanical duct install continues in the classroom buildings.
Overall Site Photo
Overall site progress as of 7/21/2021.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Wall framing, sheathing and interior mechanical, electrical and plumbing rough-in is ongoing. Exterior Framing and sheathing continues on the South side.
Classroom Building
Activity: Interior mechanical, electrical and plumbing rough-in is ongoing. Interior framing continues on all levels.
CTE Classroom Building
Activity: Concrete slab-on-metal deck has been poured on level 2 and polished concrete pours continue on level 1.
Classroom Building
Activity: Exterior framing is ongoing. On the interior, floor grinding, duct install and stair install continues.
Performing Arts Building
Activity: Forming at the orchestra pit walls is ongoing. Waterproofing and conduit connection work continues.
Commons Area
Activity: Metal decking install on level 2 is ongoing.
Athletic Wing
Activity: Fire Sprinklers are being installed. Temporary roof install is ongoing.
Progress Photos
Project Update: July 12-23
Orchestra Pit Walls
Orchestra pit walls are poured in the Theater.
Commons Building
Progress on the commons building. Decking and steel install continues while underground plumbing and electrical installs below.
Courtyard Area
Progress on all buildings surrounding the future courtyard
Overall Site Photo
Overall site progress as of 8/10/2021.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Interior mechanical, electrical and plumbing rough in on level 3 is in progress.
Classroom Building
Activity: Interior mechanical, electrical and plumbing rough-in is ongoing on level 3. Interior soffit framing continues.
CTE Classroom Building
Activity: Rough grind on polished concrete and floor protection on level one is in progress.
Classroom Building
Activity: Exterior framing is ongoing. On the interior, stair, duct and plumbing install continues.
Performing Arts Building
Activity: Orchestra pit walls have been pooured. Catwalk steel, decking and handrail welding is ongoing.
Commons Area
Activity: Metal decking install and welding on level 2 is ongoing. Underground plumbing and electrical work continues
Athletic Wing
Activity: Polished concrete coriddor poured. Duct work and electrical rough in continues.
Progress Photos
Project Update: July 26 - August 13
Project Logistics
Hover on icons for details on highlighted areas
Entrance Gate 1
Entrance Gate 2
Entrance Gate 3
Material Laydown Area
Pedestrian Walkway
Parking
Main Building Construction
Office Trailers
Classroom Wing Hallway
Progress in the classroom wing hallway on level 1.
Commons Staircase
Construction of the staircase in the commons building
Athletic Building
Hallway progress between the locker rooms and gymnasium
Overall Site Photo
Overall site progress as of 9/2/2021.
Progress Photos
Project Update: August 16 - September 1
Welcome back Mountain View Students and Staff!
Click to play the welcome back video below
Gym Wall
The North gym wall with the Dark Thunder Blue coating the bottom.
Auditorium Seats
Finishing Concrete pours for seating in the auditorium.
Bathroom Tile
Bathroom tile continues in process.
MVHS Classroom Wing
Drywall and window sealant process continues.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Polishing corridors and classroom floor finish prep.
Classroom Building
Activity: Tile in bathrooms near complete and interior painting continues.
CTE Classroom Building
Activity: Full install for roof along with framing and glass install.
Classroom Building
Activity: Taping on level 2 & 3, and brick washing with glazing.
Performing Arts Building
Activity: Forming Auditorium Stairs and window flashing.
Commons Area
Activity: Flashings and Window prep, started Main Entrance Canopy.
Athletic Wing
Activity: Sheetrock and Taping continues along with painting of main gym and locker rooms.
Progress Photos
Project Update: December 2021
Auditorium Seats
Finishing Concrete pours for seating in the auditorium.
Athletic Wing
Hallway of main athletic wing to gyms and locker rooms. Continuing drywall instalization along with paint application.
MVHS Classroom Wing
Drywall and window sealant process continues with polished floors.
Main Gymnasium
Side hoops have been installed in the main gym. Thunder blue paint also applied.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Tile at level 3 along with casework at level 1.
Classroom Building
Activity: Painting at level 2 and 3 along with lighting trim at 2 and 3.
CTE Classroom Building
Activity: Aluminum window frames and glass at bridge install.
Classroom Building
Activity: Caulking along with stairwell framing completed.
Performing Arts Building
Activity: Framing is contuining. Theater Panel grinding complete.
Commons Area
Activity: Columns were build at main entrance canopy. Kitchen intall started.
Athletic Wing
Activity: Started Tile at Locker rooms, while also completing taping in weight room.
Progress Photos
Project Update: January 2022
Auditorium Seats
Finishing Concrete pours for seating in the auditorium.
Gym Wall
The North gym wall with the Dark Thunder Blue coating the bottom.
MVHS Classroom Wing
Drywall and window sealant process continues.
Bathroom Tile
Bathroom tile continues in process.
Progress Photos
Project Update: December 2021
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Polishing corridors and classroom floor finish prep.
Classroom Building
Activity: Tile in bathrooms near complete and interior painting continues.
CTE Classroom Building
Activity: Full install for roof along with framing and glass install.
Classroom Building
Activity: Taping on level 2 & 3, and brick washing with glazing.
Performing Arts Building
Activity: Forming Auditorium Stairs and window flashing.
Commons Area
Activity: Flashings and Window prep, started Main Entrance Canopy.
Athletic Wing
Activity: Sheetrock and Taping continues along with painting of main gym and locker rooms.
Progress Photos
Project Update: January 2022
Skybridge
Finishing up curtainwall installation on skybridge.
Athletic Wing
Sloped ceiling being installed in athletic wing outside of main gym.
Locker Room Tile
Tile finishes are underway in the locker room showers within the athletic wing.
MVHS Greenhouse
Footings forms for greenhouse continue to be built.
Project Highlights
Tap icons for more information
Science Classroom Building
Activity: Interior is being prepped for sheetrock. Building has temporary heat.
Classroom Building
Activity: Windows, metal panels and brick vaneer install is ongoing.
CTE Classroom Building
Activity: Interior framing and exterior WRB (Water Resistive Barrier) install continues.
Classroom Building
Activity: Duct and plumbing rough in continues while brick veneer and metal panel install begins on the exterior.
Performing Arts Building
Activity: Auditorium steel decking install and HVAC layout continues.
Commons Area
Activity: Pouring polished concrete, started interior framing.
Athletic Wing
Activity: Wall framing, door frame install and overhead mechanical work is ongoing.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Dropping tile in ceiling while carpet and rubber base is close to finishing.
Classroom Building
Activity: Finishing up level 1 concrete floor polish, carpet and rubber base.
CTE Classroom Building
Activity: Finishing up hanging sheetrock along with hanging hard lids.
Classroom Building
Activity: Bridge storefront and glazing complete. Interior finish install continues.
Performing Arts Building
Activity: Continued framing at support rooms and stage painting.
Commons Area
Activity: Continuing admin top out along with continued concrete floor grinding.
Athletic Wing
Activity: Painting in wrestling room and finishing up tile in boys and girls facilities.
Project Update: February 2022
Progress Photos
Locker Rooms
Locker Installation begins in PE Locker rooms.
Football Field
Fine grading continues at the football field to prep for turf installation.
Polished Concrete Floors
Polished concrete hallways in classroom building
CTE Building
Drywall installation is ongoing in the shop classrooms in the CTE Building.
Progress Photos
Project Update: March 2022
Restrooms
Toilet partitions installed in restrooms.
Classroom Wing
Hallway nearly complete in classroom building.
Main Gym
Wood flooring installed in main gym.
Overall Site Photo
Overall site photo taken 04/29/2022.
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Final Cleaning is ongoing.
Classroom Building
Activity: final paint and final cleaning is ongoing.
CTE Classroom Building
Activity: Casework , ceiling grid and paint install continues.
Classroom Building
Activity: Casework install and final paint is ongoing.
Performing Arts Building
Activity: Drywall installation continues in theater.
Commons Area
Activity: Perforated ceiling tile install is ongoing, paint and sinage install on level 1 continues
Athletic Wing
Activity: Installing bleachers and final paint in locker rooms
Progress Photos
Project Update: April 2022
Restrooms
Toilet partitions installed in restrooms.
Classroom Wing
Hallway nearly complete in classroom building.
Main Gym
Wood flooring installed in main gym.
Overall Site Photo
Overall site photo taken 04/29/2022.
Project Highlights
Tap icons for more information
Science Classroom Building
Activity: Final Cleaning is ongoing.
Classroom Building
Activity: final paint and final cleaning is ongoing.
CTE Classroom Building
Activity: Casework , ceiling grid and paint install continues.
Classroom Building
Activity: Casework install and final paint is ongoing.
Performing Arts Building
Activity: Drywall installation continues in theater.
Commons Area
Activity: Perforated ceiling tile install is ongoing, paint and sinage install on level 1 continues
Athletic Wing
Activity: Installing bleachers and final paint in locker rooms
Progress Photos
Project Update: April 2022
Overall Site Photo
Overall site photo (06/22/2022)
Auditorium
Seating, floor, wall, and ceiling progress
Sector C
Sector C MV paneling in progress
Courtyard
Courtyard flatwork in progress
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Owner move in and Contractor Punch corrections
Classroom Building
Activity: Owner move in and Contractor Punch corrections
CTE Classroom Building
Activity: Millwork, Contractor Punch corrections, and Electrical / Low Voltage trim
Classroom Building
Activity: Stair #3 guardrail mesh complete and Nutrition Lab stainless install
Performing Arts Building
Activity: Auditorium paint, stage floor boxes, and wall / ceiling trim
Commons Area
Activity: MV paneling / lighting and Kitchen equipment / counters
Athletic Wing
Activity: A/B Gym game line layout and corridor stenciling
Progress Photos
Project Update: June 2022
Overall Site Photo
Overall site photo (07/12/2022)
Courtyard
Courtyard flatwork complete
Sector C
Sector C Commons progress
Sector H
Sector H Final Clean progress
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Contractor Punch corrections
Classroom Building
Activity: Contractor Punch corrections
CTE Classroom Building
Activity: Final clean and Punch corrections
Classroom Building
Activity: Punch corrections and Equipment / Plumbing final connections
Performing Arts Building
Activity: Stage Floor installation
Commons Area
Activity: MV paneling complete, Subway stainless counters, Concrete Floor polish, and Elevator final adjustments
Athletic Wing
Activity: Electrical and Fire Alarm finals
Progress Photos
Project Update: July 2022
Overall Site Photo
Overall site photo (05/20/2022)
Commons
Commons Ceiling Progress
Weight Room
Weight and wrestling room flooring in progress
Greenhouse
Greenhouse structure in progress
Project Highlights
Click icons for more information
Science Classroom Building
Activity: Final paint and contractor punch
Classroom Building
Activity: Final paint and contractor punch
CTE Classroom Building
Activity: Floral cooler install and casework / ceiling grid install continues.
Classroom Building
Activity: South stair stainless mesh and final paint
Performing Arts Building
Activity: Music basework / sound booth install
Commons Area
Activity: Kitchen casework / equipment installed
Athletic Wing
Activity: Weight and wrestling flooring
Progress Photos
Project Update: May 2022
Progress Photos
Project Update: September 2022
Home
JV Softball Field
Final grading in progress.
Fence posts and mow band installed.
Softball Batting Cages
Perf pipe, drain rock, drain fabric, fence posts, and mow band installed.
JV Baseball Field Retaining Wall
Acid etched retaining wall and net posts installed.
Varisty Baseball Field
Drain rock install in progress.
Progress Photos
Project Highlights
Click icons for more information
Varsity Baseball
Activity: Fine grading subgrade
JV Softball
Activity: Placing drain rock.
Varsity Softball
Activity: Fine grading subbase
Lot 5
Activity: Setting string line and forms for curbs
Phase 1
Activity: Fully operational high school!
JV Baseball
Activity: Haul off and grading.
Athletic Wing
Activity: Electrical and Fire Alarm finals
Restrooms
Toilet partitions installed in restrooms.
Classroom Wing
Hallway nearly complete in classroom building.
Main Gym
Wood flooring installed in main gym.
Overall Site Photo
Overall site photo taken 05/20/2022.
Project Highlights
Tap icons for more information
Science Classroom Building
Activity: Final Cleaning is ongoing.
Classroom Building
Activity: final paint and final cleaning is ongoing.
CTE Classroom Building
Activity: Casework , ceiling grid and paint install continues.
Classroom Building
Activity: Casework install and final paint is ongoing.
Performing Arts Building
Activity: Drywall installation continues in theater.
Commons Area
Activity: Perforated ceiling tile install is ongoing, paint and sinage install on level 1 continues
Athletic Wing
Activity: Installing bleachers and final paint in locker rooms
Progress Photos
Project Update: May 2022