Project Details
Mobilization
June 2026
Ground Breaking
Sep 2026
Structure
Complete
Q2 2027
Substantial Completion
Dec 2028
Higher Education
A new Chemical Sciences Building will make that possible as a nexus for collaborative research and teaching that will help UW define the next 100 years of science education and breakthroughs.
Design
The UW Chemistry Department’s core research and instructional functions are constrained by aging, fragmented facilities that no longer meet the requirements of modern scientific practice. Key buildings—specifically the Chemistry Library Building (1957)—lack the infrastructure, environmental controls, and spatial flexibility needed to support contemporary research, competitive faculty recruitment, or high-quality student training. These limitations restrict wet-lab instruction, impede interdisciplinary collaboration, and reduce the university’s competitiveness for major research funding.
Partnerships within this project
Location:
Seattle, WA
The Building:
104,100-SF
University of Washington
Chemical Sciences Building
Coming Q1 2026
State-of-the-art construction
A new Chemical Sciences Building (CSB) will enable a new mode of science where fundamental chemical research can transform into real-world applications in real-time.
Watch the new Central Laboratory take shape
Construction Updates
104,100-SF of:
Laboratory Spaces
Common Collaboration Spaces
Meeting Rooms
Office Spaces
Will house the chemistry research labs currently housed in Bagley Hall and the Chemistry Library
Forensic Biology
Fifteen percent efficiency gain
Latent Prints and Impressions
Flexible, state-of-the-art lab design
Toxicology
Space for hands-on, independent research projects
Statewide Administration
Chemical Sciences Building Renderings
Biology Laboratory
Chemistry Laboratory
Interior spaces for the OCME include:
Anthropology
Autopsy Suite
Fatality Review Programs
Histology
Mass Disaster Response
Medicolegal Investigation
Radiological Services
For additional information on this project, please contact
the UW Construction Manager.
Questions about this project?
State Anatomical Program
Statewide Administration
Skanska.com
Follow Us
The Project
Construction Updates
The Team
The Facts
What's New
Contact
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Month
Previous
Next
Erosion and sediment control measure installation
Grading and earthwork
Groundbreaking Ceremony
MAR 2023
Erosion and sediment control measure installation
Grading and earthwork
FEB 2023
Concrete foundations south portion of the building
Mechanical, electrical, and plumbing underground installations
Forming ballistic range concrete walls
CMU installation for
Stairwell #4
Excavation for the North Stormwater Detention Basin
North portion of the building pad stoned and ready for foundations
Screening and hauling topsoil
APR 2023
JUL 26
JUN 26
AUG 26
2026
2027
2028
Check back monthly for updates as the Chemical Sciences Building takes shape.
Construction Updates
SEP 26
Concrete foundations progressing, with expected completion in June
Site utility work including domestic, sanitary, and
fire-water lines is ongoing
North underground stormwater detention system nearing completion
CMU installation for Stair 4 expected completion early June
MAY 2023
Concrete foundation installation completed this month
Stair 4 CMU installation completed this month. Metal pan stair installation has begun
Stair 2,3 and elevator 3 and 4 CMU installation ongoing
Concrete wall installation is progressing at loading dock areas
CMU Installation for Stairwell #4
JUNE 2023
South stormwater detention system nearing completion
Roadwork on Times Dispatch is ongoing; expected to be complete in July
Site utility work including domestic, sanitary, storm, and fire-water lines is ongoing
Underground utilities
being worked on by all subcontractors
Plumbing progressing for underground on east section of the north building
Stair 3 CMU installation completed this month
CMU Installation for stair 1
in progress
CMU installation for elevator 3 & 4 nearing completion
Forming of retaining wall inside mechanical courtyard
JULY 2023
NOV 26
DEC 26
CMU installation of stair 5
in progress
Completion of stair 1
CMU installation for elevator 1 and 2 in progress
Concrete pour on northside of building
Structural steel started on south building on east end
Site utilities ongoing
AUGUST 2023
Site grading activities ongoing
JAN 27
FEB 27
CMU Installation of stair towers complete
Concrete pour for north building and connector to be completed this week
Installation of metal decking sequence 1-6 on south building
Structural steel progressing to west end of the south building
Mechanical, electrical, and plumbing hangers’ sequence 1-6 starting this week
Stone being installed around the perimeter of site
SEPTEMBER 2023
Elevated slab pours on
east-end for levels 2 and 3
Structural steel nearing completion on west end of the south building
Final slab on grade pour to be completed this week on the north building
Stone base for temporary drive lane ongoing around perimeter of site
Mechanical, electrical, and plumbing hangers’ continuing to follow metal deck installation
OCTOBER 2023
MAR 27
Underground for fire hydrants complete
50% complete on north building for steel erection
Mechanical sleeves and hangers ongoing
Topping off party set for December 20th
Masonry veneer being installed on loading dock
NOVEMBER 2023
Loading dock set to be completed by end of month
Fireproofing continuing on level 3 area C
APR 27
Initial pass of curb and gutter at west and south building complete
Topsoil around site continues
Structural steel nearing completion
Spray Fireproofing installation is ongoing
Interior and Exterior metal stud framing
Interior and Exterior CMU underway
Overhead MEP and Fire Protection rough-in proceeding
DECEMBER 2023
Wrapping up storm sewer installation on the westside of the site
Spray fireproofing installation is ongoing
North building roof screen and windowsill support being installed
Movement of topsoil
around site ongoing
Finishing up CMU installation in the south building
Interior priority wall framing ongoing throughout south building
Prepping for last couple of elevated slab pours
JANUARY 2024
Exterior framing and sheathing ongoing in south building
CMU installation at the
north building loading dock continues
Last major concrete pour completed this week
MEP overhead rough-in continues in south building
Fireproofing is ongoing in the southern portion of north building
Exterior metal stud framing is ongoing in the north building.
Curtain Wall installation has begun at the east elevation
of south building
Roofing ongoing at the South Building Penthouse
FEBRUARY 2024
JUN 27
Prepping for placement of base level asphalt
Exterior, Framing and Sheathing is ongoing in the South Building, Connector and North Building
Exterior and interior CMU installations continued in the North Building
Interior MEP rough in is ongoing in the South Building
MARCH 2024
Base paving from entrance, one to south parking lot complete
Equipment pad pours are ongoing
Curtainwall is being installed at the South Building and Connector
Interior MEP in wall and above ceiling rough in continues in the South Building
APRIL 2024
Priority wall framing continues in the Connector and North Building
Roofing is ongoing in the South Building main roof and North Building low roof
Brick started in the equipment yard
Brick Veneer is being installed on the loading dock screen walls and in the equipment yard
AUG 27
JUL 27
SEP 27
Roofing activities ongoing on South & North building
MAY 2024
Elevations of the Connector in the East and West continues
Vapor barrier installation completed on Main Roof in the South Building
Curtainwall and glazing activities started on the Northwest and South Elevations
Completion of installation of Duct and Pipe supports on Level 2 and 3 of the North Building Roof and Main Roof of the South Building
MEP above-ceiling rough-in ongoing
OCT 27
MEP above-ceiling rough-in continues
Above Level 2 connector roof expected to start next month
Elevator 3 and 4 installations expected to start early August
Brick installation complete on Northeast Elevation of the South Building, and North Elevation North Building
Completion of the South Building Northeast Elevation curtain wall
JULY 2024
Completion of in-wall inspections on Level 1 and Level 2 South Building
Roofing activities continue on the North Building and Connector
Elevator 3 and 4 nearing completion
Start of Metal Panel installation on the East elevation of the South Building
AUG 2024
NOV 27
Priming and first coats continue on Level 1 of the South Building
Elevator 3 and 4 installations complete
Drywall installation continues on Level 1 and Level 2 of South Building
Roofing system installation near completion
SEPT 2024
DEC 27
Completion of the North Building East elevation curtain wall
JAN 28
Interior activities continue throughout
MEP above-ceiling rough-in ongoing
Exterior façade progress continues
Completion of the Clerestory roof, connector corridor roof and OCME Penthouse Roof
Brick installation completed on the South elevation South Building and East elevation North Building
JUNE 2024
Above ceiling MEP rough-in continues
Ceiling grid activities began on Level 1 in the South Building
Substantial completion of drywall on Levels 1 and 2 in the South Building
Completion of the North Building and North Elevation Curtain Wall
OCT 2024
MAR 28
Points of Interest
NOV 2024
DEC 2024
APR 28
Above ceiling MEP rough-in continues
Drywall installation nearing completion on South Level 3 and Connector Level 1
South Building loading zone leave out is being closed up
Metal panel installation continues on multiple elevations
Ceiling grid activities continue on Level 1 in the South Building
Paint installation continues on Level 2 South Building
Above ceiling MEP rough-in continues
Paint continues on Level 3 South Building
Ceiling grid has started on Level 2 South Building
Drywall installation ongoing in North Building Level 1
South Building louver installation is ongoing
Metal panel installation continues on multiple elevations
Project milestone of conditioned air in South Building
Ceramic tile installation complete on Level 1 South Building
Drywall installation continues in North Building Level 2
Interior finishes continue in South Building
Completion of metal panel installation in northeast South Building and west half of North Building
JAN 2025
MAY 28
Working towards conditioned air in the North Building
Epoxy and resilient flooring started on Level 1 South Building
In-wall inspections completed in North Building Level 1 East
Above ceiling rough-in continues on Level 3 in South Building and 1-3 in North Building
Completion of metal panel installation on North Building West elevation
FEB 2025
JUN 28
Lab casework and lab equipment installation began on Level 1 of the South Building
Ceramic tile installation completed on Level 2 South Building and beginning on Level 3
Drywall installation continued on Level 3 in the North Building
Completion of metal panel installation on the South Building Penthouse, South Elevation and North Building Elevation
MAR 2025
JUL 28
AUG 28
Architectural casework and wood door installation expected to start next month
Conditioned air has been achieved in the North and South Building
Installation of firing range equipment complete
Exterior site work resumed with the installation of the walking path, site lighting, and final grading
APR 2025
Hard (drywall) ceiling installation is ongoing on Levels 1 and 2 of the North Building
Resilient flooring completed on Level 2 and 3 of South Building
Architectural casework and wood casework installation completed in Levels 1 and 2 of the South Building
Placement of sidewalks, parking lot island curb/gutter, walking paths, and site lighting bases ongoing
MAY 2025
Terrazzo flooring completed in the North Building (Autopsy Suite)
SEP 28
Terrazzo flooring completed in the connector main lobby and second floor
Hard (drywall) ceiling installation is expected to be completed this month on Levels 1 and 2 of the North Building
Architectural wood casework installation completed on Levels 2 and 3 of North Building
MEP drops to grid and trim out activities continue throughout building
Metal panel installation complete on the west elevation of the connector
JUNE 2025
OCT 28
Epoxy wall coating installation in Level 1 area E completed this month
Setting of embalming stations, neuropathology equipment, body racks and backdraft autopsy tables in North building Area E
Sliding automatic entrances in Area E began this month
Ceiling tile installation throughout the building
Metal panel installation complete at the south and main entry canopy
JULY 2025
NOV 28
Installation of the morgue autopsy equipment continues in North Building Area E
Wood ceiling installation started on Level 1 South Building
Sallyport overhead coiling door install complete
Carpet installation expected to begin next month
Sheet vinyl flooring installation is ongoing in North Building Level 1 and 2
AUG 2025
DEC 28
JAN 29
Carpet installation began at the end of this month
Sliding automatic entrances nearing completion
Wall-mounted lab accessory installation continues throughout
Test and balancing activities are ongoing in the South Building
Main entry paver plaza and site lighting bases are nearing completion
SEP 2025
FEB 29
MAR 29
Coping and roof trim metal nearing completion
Epoxy flooring began in the North Building Penthouse
BAS systems, fire alarms, and other low voltage systems being tested
Final asphalt paving to be near completion next month
Final paint complete on Levels 1 and 2 of the North Building
OCT 2025
Final and fine grading, as well as topsoil distribution and landscaping completed
this month
Mechanical, electrical, and plumbing trim-out activities ongoing
Lighting protection installation was completed this month
Placement of concrete sidewalks , parking lot curb/gutter, and walking paths is complete
Storefront and interior glazing installation completed this month in the South Building, Connector, Main Lobby, and North Building
NOV 25
Final inspections of elevators 1-4
Testing and balancing activities ongoing
Site work continues with installation of exterior furnishings
Mobilize on site
JUN 2026
The College is committed to providing a world-class education to its students while fostering leading-edge research across our units. The new Chemical Sciences Building will be a vital hub for interdisciplinary sciences and education that positively impacts our campus and region. We invite our community of donors to invest in this project alongside the College and help us lay the foundation for the next generation of learning and discovery.
Dianne Harris
Dean, College of Arts & Sciences
Project Type:
Design Build
Exterior Skin Complete
Mar 2028
You have selected a future date.
Check back for updates as construction continues.
You have selected a future date.
Check back for updates as construction continues.
You have selected a future date.
Check back for updates as construction continues.
OCT 26
MAY 27
FEB 28
2029
For additional information on this project,
please contact the UW Construction Manager.
Contact now
Meet the Team
Department of Forensic
Science Team Members
Department of General
Services Team Member
UW Construction Manager
Garret Olsen
(206) 798-2607
garreto@uw.edu
Deputy Director of
Forensic Science
David A. Barron PhD
Project Manager–
Special Projects
Mary Ann Petry
Lead Architect
Design Team
Payette Associates Inc
Boston, MA
Account Manager
Skanska Team Members
Rob Robinson
Project Manager
Molly Roe
Sr. Superintendent
Jerry Wells
Project Executive
Margot vanSwearingen
Assistant Project Manager
Samuel Stargell
IPD Process Integrator
Ryan Kline
Superintendent
Lisa Lacy
Sr. Project Engineer
Jordan Nelson
EHS Manager
Zach Davis
Senior Field Administrator
Tyra Gore
Project Engineer
Alec Williams
Senior Project Manager
Neal Whaley
Regional Diversity Manager
Sheila Bowles
Questions about this project?
Skanska.com
Follow Us
The Project
Construction Updates
The Team
The Facts
What's New
Contact
Learn more about Matt
16 years
How long have you been with Skanska?
Project Director
Matt Kidwell
Rewarding
How would you describe working at Skanska in one word?
I worked in construction as a high school job before college and liked how all the different pieces and parts come together to create a finished product.
What inspired you to pursue a career in construction in one sentence?
I like to wakeboard, snowboard, mountain bike, and play golf in my free time.
What is an interesting fact about you?
All of the different specialty lab spaces that are used to complete the forensic work for both DFS and OCME.
What is your favorite part of the new Central Lab?
In my role I help the construction team to develop a plan and approach for the project and support them throughout by helping to remove obstacles so that at the end of the day we are all successful and the owner gets a brand new high quality facility.
What parts of the construction do you manage as part of your role on the project?
7.5 years
How long have you been with Skanska?
Inspiring
How would you describe working at Skanska in one word?
Every day is different.
What inspired you to pursue a career in construction in one sentence?
Native of Buffalo, NY – Go Bills!
What is an interesting fact about you?
Overnight accommodations for 300 bodies.
What is your favorite part of the new Central Lab?
The contract and client when needed.
What parts of the construction do you manage as part of your role on the project?
Account Manager
Mark Balling
Learn more about Mark
16 years
How long have you been with Skanska?
Family
How would you describe working at Skanska in one word?
My Dad.
What inspired you to pursue a career in construction in one sentence?
I coached Youth Sports for 20 years.
What is an interesting fact about you?
The South Building.
What is your favorite part of the new Central Lab?
Field Sr. Leader
What parts of the construction do you manage as part of your role on the project?
Sr. Superintendent
Richard Conage
Learn more about Alec
Since July 2022
How long have you been with Skanska?
Fulfilling
How would you describe working at Skanska in one word?
I like a team-based environment and working with other professions/trades on a daily basis.
What inspired you to pursue a career in construction in one sentence?
I can hold my breath longer than Tom Cruise (over 6 minutes).
What is an interesting fact about you?
The ballistics range.
What is your favorite part of the new Central Lab?
Document control management.
What parts of the construction do you manage as part of your role on the project?
Project Engineer
Alec Williams
Learn more about Tyra
Since April 2022
How long have you been with Skanska?
Purposeful
How would you describe working at Skanska in one word?
I wanted to make an impact in building for a purpose and a better community.
What inspired you to pursue a career in construction in one sentence?
I have never been on an airplane.
What is an interesting fact about you?
All of it. I am excited to be a part of something that will aid in the advancement of the criminal justice system.
What is your favorite part of the new Central Lab?
Field Administration
What parts of the construction do you manage as part of your role on the project?
Field Administrator
Tyra Gore
Assistant Project Manager
Ashley Keane
VDC Manager
Seth Shaver
Superintendent
Derek Matuszczak
(206) 798-2607
garreto@uw.edu
(206) 798-2607
garreto@uw.edu
Lara Sirois
(206) 335-2545
lsirois@uw.edu
UW Project Manager
EHDD
Seattle, WA
Associate Architect
GGN
Seattle, WA
Landscape Architect
KPFF
Seattle, WA
Consulting Engineer