Mountain View High School Project Updates

Project Update: September 2022

Progress Photos

Progress Photos

Softball Batting Cages

Perf pipe, drain rock, drain fabric, fence posts, and mow band installed.

JV Softball Field

Final grading in progress. Fence posts and mow band installed.

Project Highlights

Click icons for more information

Project Update: July 2022

Progress Photos

Courtyard

Courtyard flatwork complete

Overall Site Photo

Overall site photo (07/12/2022)

Project Highlights

Click icons for more information

Project Update: June 2022

Progress Photos

Auditorium

Seating, floor, wall, and ceiling progress

Overall Site Photo

Overall site photo (06/22/2022)

Project Highlights

Click icons for more information

Project Update: May 2022

Progress Photos

Commons

Commons Ceiling Progress

Overall Site Photo

Overall site photo (05/20/2022)

Project Highlights

Click icons for more information

Project Update: April 2022

Progress Photos

Main Gym

Wood flooring installed in main gym.

Overall Site Photo

Overall site photo taken 04/29/2022.

Project Highlights

Click icons for more information

Project Update: March 2022

Progress Photos

Football Field

Fine grading continues at the football field to prep for turf installation.

Polished Concrete Floors

Polished concrete hallways in classroom building

Locker Rooms

Locker Installation begins in PE Locker rooms.

CTE Building

Drywall installation is ongoing in the shop classrooms in the CTE Building.

Project Update: February 2022

Progress Photos

Skybridge

Finishing up curtainwall installation on skybridge.

Athletic Wing

Sloped ceiling being installed in athletic wing outside of main gym.

Project Highlights

Click icons for more information

Project Update: January 2022

Progress Photos

Main Gymnasium

Side hoops have been installed in the main gym. Thunder blue paint also applied.

Auditorium Seats

Finishing Concrete pours for seating in the auditorium.

MVHS Classroom Wing

Drywall and window sealant process continues with polished floors.

Athletic Wing

Hallway of main athletic wing to gyms and locker rooms. Continuing drywall instalization along with paint application.

Project Highlights

Click icons for more information

Project Update: December 2021

Progress Photos

MVHS Classroom Wing

Drywall and window sealant process continues.

Bathroom Tile

Bathroom tile continues in process.

Project Highlights

Click icons for more information

Overall Site Photo

Overall site progress as of 9/2/2021.

Athletic Building

Hallway progress between the locker rooms and gymnasium

Project Update: August 16 - September 1

Welcome back Mountain View Students and Staff!

Click to play the welcome back video below

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Progress Photos

Commons Staircase

Construction of the staircase in the commons building

Classroom Wing Hallway

Progress in the classroom wing hallway on level 1.

Project Update: July 26 - August 13

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Project Logistics

Hover on icons for details on highlighted areas

Progress Photos

Overall Site Photo

Overall site progress as of 8/10/2021.

Commons Building

Progress on the commons building. Decking and steel install continues while underground plumbing and electrical installs below.

Courtyard Area

Progress on all buildings surrounding the future courtyard

Orchestra Pit Walls

Orchestra pit walls are poured in the Theater.

Project Highlights

Click icons for more information

Project Update: July 12-23

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Progress Photos

Overall Site Photo

Overall site progress as of 7/21/2021.

Commons Building

Metal decking is now installed on the commons building.

Classroom Wing

Interior framing, plumbing and mechanical duct install continues in the classroom buildings.

Exterior Weather Barrier

Weather barrier is being installed on the new athletic building.

Project Highlights

Click icons for more information

Project Update: June 21 - July 9

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

One Year Later

One year ago, the first drone photos were taken before construction began on Mountain View High School. Click through the photos below to see the progress made in just a year.

April 2021

May 2021

November 2020

December 2020

January 2021

February 2021

March 2021

June 2020

September 2020

October 2020

June 2021

August 2020

One Year of Progress

June 2021

June 2020

Project Update: June 14-18

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Progress Photos

Overall Site Photo

Overall site progress as of 6/18/2021.

Mechanical Duct Rough-In

Mechanical duct rough-in is ongoing in the classroom buildings.

Interior Framing

Interior framing and rough in continues in the classroom buildings.

Commons Building

Structural steel erection continues in the commons building.

Project Highlights

Click icons for more information

Project Update: June 7-11

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Drone Photos

Overall Site Photo

Overall site progress as of 6/10/2021.

Theater Catwalks

The catwalks in the theater are installed and the braces holding up the walls will be removed starting next week.

Exterior Framing

Framing continues on the classroom building on the South end of the site.

CTE Classroom Building

Progress on the CTE classroom building.

Project Update: May 17-June 4

June 3rd Beam Signing

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Progress Photos

Exterior Framing

Exterior framing work is ongoing on the North side of the new classroom wing.

Stair Installation

Stairs are being installed in the new classroom building.

Site Overview

Overall site progress as of May 28th, 2021.

Concrete Columns

These are the concrete columns that will support the future library.

Project Highlights

Click icons for more information

Project Update: May 3-15

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Progress Photos

Building Mock-Up

This picture shows the nearly completed building Mock-up.

Locker Rooms

This photo shows the work happening in the future locker rooms. These rooms will be poured with concrete by the end of the week.

Site Overview

This photo shows the overall site progress as of May 12th, 2021.

Theater Catwalk

This photo shows one of the new catwalks in the theater.

Project Highlights

Click on icons for more information

Project Update: April 19-30

Progress Photos

Site Overview

This photo shows the overall site progress as of April 30th, 2021

Classroom Building

This picture shows exterior framing being installed on the north side of one of the classroom buildings

Tilt Panels

This photo shows the largest concrete tilt panel on this project weighing in at 240,000lbs!

Skybridge

This photo shows the construction of the skybridge that connects two of the new classroom buildings.

Drone Photos

Click the arrows to see more drone photos

Project Update: April 5-17

Highlights from this week

Click icons for more information

Progress Photos

Slab on Metal Deck

This photo shows the concrete being finished on level 2 of the classroom wing.

Site Activity

This picture shows the last tilt panels being poured near the the future auditorium

Roof Level Work

Seen here are a few members of the decking crew installing metal decking at the roof level on one of the classroom buildings.

Athletic Building

This photo shows a crane placing metal decking in the new athletic building

Project Update: March 22-April 3

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Level 2 Layout

This photo shows the mechanical, electrical and plumbing (MEP) layout work happening on level 2 of the classroom buildings.

Clasroom Building

This photo shows the new classroom building and the stair tower installed for access to each level.

Althletic Building

This picture shows the joists in the new wrestling room.

Tilt Panels

Seen here are the tilt panels being finished after the concrete was poured earlier in the day.

Project Update: March 15-20

Highlights from this week

Tap icons for more information

Tap here to see what is happening LIVE

Project Update: March 8 - 12

Video Player is loading.
Loaded: 0%
Current Time 0:00
Duration 0:00
Remaining Time 0:00
 
1x

Photos from this week

Tilt Panels

Seen here are the tilt panels being placed by a crane. In only a week all of the walls in the new athletic wing were erected.

Steel Columns

This week steel columns are being placed in one of the classroom buildings.

Project Update: March 1 - 6

Tilt panel forms

Lower level of the auditorium

New locker room tilt panels

22250 Crane

Highlights from this week

Skanska USA is one of the largest construction and development companies in the U.S., serving a broad range of clients. Headquartered in New York City with offices in 29 metro areas, we have more than 7,600 employees committed to being leaders in safety, project execution, sustainability, ethics and people development.

We have been active in the Pacific Northwest market since 1946. For the last five years, our local team has won an average of $625 million of work each year across a wide range of markets—including government, commercial, healthcare and high-tech—in both the public and private sectors. With a dedicated staff of more than 300 employees in Oregon and Southwest Washington, Skanska combines local presence with national resources to build a more sustainable future for our customers and communities.

Skanska USA Building Inc. 1010 NW Flanders St. Suite 500 Portland, OR 97209 503.382.0900

Connect with us

Powered by Ceros